AGORA
Project title: Advanced coGeneration Options for Reintegrating local Assets
DTP Project Acronym: AGORA
Programme priority: Priority 4
Programme priority specific objective: SO 4.1 Improve institutional capacities to tackle major societal challenges
Name of the lead partner organization: Cluj-Napoca Municipality
Project duration: 30 months (01.07.2020 – 31.12.2022)
Project budget: 2,396,870.05 EUR of which by financing sources:
Source 1- European Regional Development Fund ERDF: 1,892,131.33EUR
Source 2- Instrument for Pre-Accession Assistance IPA II: 74,580.64 EUR
Source 3- European Neighbourhood Instrument (ENI-MD / ENI-UA): 70,627.55 EUR
Project web page: http://www.interreg-danube.eu/approved-projects/agora
Facebook: @ InterregAGORA (https://www.facebook.com/InterregAGORA)
Twitter: @InterregAGORA
DanuP-2-Gas
Title : Innovative model to drive energy security and diversity in the Danube Region via combination of bioenergy with surplus renewable energy
Acronym : DanuP-2-Gas
Funding program : DTP Interreg
Programme priority : Priority 3
Programme priority specific objective : SO 3.2 Improve energy security and energy efficiency
Project Code : DTP 3 – 745 – 3.2
Project budget : 2,553,726,85 EUR
Funding sources : European Regional Development Fund (ERDF) – 2,109,336,02 EUR, Instrument for Pre-Accession Assistance (IPA) – 61,331,75 EUR , European Neighbourhood Instrument (ENI) – 0,00 EUR
Lead Applicant : Technology Centre Energy – University of Applied Sciences Landshut
Project duration : 30 months (01.07.2020 – 31.12.2022)
ISTER
Project title: ConnectIng hiSTorical Danube rEgions Roman routes
DTP Project Acronym: ISTER
Programme priority: Priority 2
Programme priority specific objective: SO 2.2 Foster sustainable use of natural and cultural heritage and resources
Name of the lead partner organization: National Museum for the History of Transylvania
Project duration: 30 months (01.07.2020 – 31.12.2022)
Project budget: 2,067,958.95 EUR of which by financing sources:
Source 1- European Regional Development Fund ERDF: 1,957,158.95 EUR
Source 2- Instrument for Pre-Accession Assistance IPA II: 110,800.00 EUR
Source 3- European Neighborhood Instrument (ENI-MD / ENI-UA): 0.00 EUR
Project web page & social media channels: http://www.interreg-danube.eu/approved-projects/ister
Facebook: @InterregISTER (https://www.facebook.com/InterregISTER)
Twitter: @InterregISTER (https://twitter.com/InterregISTER)
Linkedin: https://www.linkedin.com/in/interreg-ister-2610741b7/
SPIRE
SPIRE is our latest Urban Innovative Actions project, financed under the 4th call of the UIA Initiative, which supports the most innovative cities of Europe in piloting yet-untested and completely novel solutions to pressing urban challenges. It is the only such project financed in the Eastern European region, and leverages on local assets and knowledge coming from our very strong national partners: the Baia Mare Municipality, Indeco soft, ARIES Transilvania, Baia Mare Metropolitan Area, the University of Agricultural Sciences and Veterinary Medicine Cluj-Napoca and the Green Energy Cluster.
BUILD-IN-WOOD
Title: Sustainable Wood Value Chains for construction of low-carbon Multi-Storey Buildings from Renewable Resources
Acronym: BUILD-IN-WOOD
Funding: Horizon 2020 | LC-RUR-11-2019-2020
Lead Applicant: Teknologisk Institut (Danish Institute of Technology)
Duration: 48 months (September 2019 – August 2023)
Website: Build-in-Wood
proGIreg
- Title: Productive Green Infrastructure for Post-industrial Urban Regeneration
- Acronym: proGIreg
- Funding: Horizon 2020 | H2020-SCC-NBS-2stage-2017
- Lead Applicant: RHEINISCH-WESTFAELISCHE TECHNISCHE HOCHSCHULE AACHEN (RWTH Aachen)
- Duration: 60 months (June 2018 – May 2023)
- Website: proGIreg
ROCK
Title: Regeneration and Optimisation of Cultural heritage in creative and Knowledge cities
Acronym: ROCK
Funding: Horizon 2020 | H2020-SC5-2016-2017
Lead Applicant: Comune di Bologna
Duration: 36 months
Website: www.rockproject.eu
CRISALIDE
Acronym: CRISALIDE – COFUND-ERANET-RUS-PLUS
Financing: the state budget
Name of the Program in NP III: European and International Cooperation – Subprogram 3.2 – Horizon 2020
Contract duration: 24 months
Contracting Authority: Executive Unit for the Financing of Higher Education, Research, Development and Innovation
Total value of the contract: 390,966.00 lei (representing EUR 84,994.00) of which on financing sources:
Source 1 – from the state budget: 270,236.00 lei (representing 58,747.00 EUR)
Source 2 – from other attracted sources (own financial contribution): 120,730.00 lei (representing 26,247.00 EUR)
Source 3 – from the European Commission: 0.00 lei (representing 0.00 EUR)